Varela, Lee, Metz & Guarino (VLMG)

Christopher M. Burke

Senior Partner

 

"Chris Burke is incredibly smart and is a strategic thinker."

- Chambers and Partners, Chambers USA Guide 2023

Chris Burke has over 20 years of experience litigating construction disputes both domestically and internationally.  Chris has tried multiple disputes through final award, with amounts in dispute of over US$1 billion.

Chris represents clients in state and federal courts and in arbitration proceedings, and has considerable experience with international dispute resolution. Chris represents owners, general contractors, construction managers, and subcontractors through the various stages of dispute resolution, from claim preservation through trial.

Before maturation of the litigation process, Chris works with his clients to avoid costly disputes by resolving issues at the project level. Once litigation is inevitable, however, Chris handles all aspects of the dispute process.  He is a seasoned litigator who protects his clients' economic interests while preparing for the best presentation at trial should a matter "go the distance."  He also advises clients on non-contentious matters, including contract drafting.

Chris is a frequent author and speaker in the construction law space and is active in both the American Bar Association and International Bar Association.

Chris graduated cum laude from Yale University and later from the University of Virginia School of Law, where he served as a Dillard Fellow Legal Research and Writing Instructor.

Representative Experience

  • Currently representing a contractor in disputes with the project owner on an 800MW offshore wind farm off the United States East Coast.

  • Currently representing a pipeline contractor in a litigation with the project owner on a water pipeline project in Pennsylvania.

  • Currently representing an EPC contractor in a AAA arbitration with the project owner on a 70MW solar power plant in North Carolina.

  • Represented an ENRS. Top 40 contractor in a AAA / ICDR arbitration with an EPC contractor on a 674MW natural gas-fired combined-cycle plant in Massachusetts. Chris served as co-lead trial counsel and following a multi-week evidentiary hearing, Chris’s client received a Final Award of over US$25 million on its claims of, among other things, lost productivity and change order work.  Chris’s client was also awarded its attorneys’ fees and costs.

  • Represented an EPC Contractor in an ICC arbitration with a subcontractor on a 600MW coal-fired plant in South America. Chris served as lead trial counsel and following a multi-week evidentiary hearing, Chris’s client received a Final Award upholding his client’s default termination, awarding in excess of US$11 million, and denying nearly all of the subcontractor’s US$30 million delay and disruption claims. Chris’s client was also awarded its attorneys’ fees and costs.

  • Represented a developer in an ICC arbitration with an EPC contractor on a 300MW coal-fired CFB power plant in Guatemala, and with a total amount in dispute of over US$1 billion. Chris served as trial counsel and following a multi-week evidentiary hearing, Chris’s client received a Final Award awarding damages of over US$300 million, and upholding his client’s default termination. Chris’s client was also awarded its attorneys’ fees and costs.

  • Represented a general contractor concerning the construction of a new 18-story courthouse in Las Vegas, NV. Chris served as trial counsel and following a 10-week arbitration hearing wherein, Chris’s client obtained a Final Award of $52.7 million on its affirmative claims and defeated nearly all of Owner Clark County's $60 million counterclaim.

  • Represented an ENR U.S. Top 30 general contractor in a dispute with a museum owner on a US$250 million modern art museum in Maryland.  The parties reached a confidential settlement prior to the trial of the matter.

  • Represented a general contractor joint venture (comprised of three ENRS. Top 50 contractors) in an arbitration concerning the design and construction of a US$1.5 billion data center in Utah. The eight-party case proceeded through one week of an American Arbitration Association evidentiary hearing before reaching settlement after Chris’s joint venture client put on its affirmative case.Represented an ENRS. Top 10 contractor engaged in a dispute with its subcontractor over the engineering and construction of a 600MW petroleum coal-fired CFB power plant. Following the first five-week phase of a scheduled eight-week arbitration hearing, during which Chris served as trial counsel, Chris's client and the opposing party were able to achieve a confidential settlement of their disputes

  • Represented an EPC contractor in an ICC Arbitration dispute with its subcontractor over performance on a 300MW solar power plant in Arizona. The parties reached a confidential settlement prior to the evidentiary hearing of the matter.

  • Represented an at-risk construction manager concerning the construction of a luxury condominium project in New York City. As co-lead trial counsel through a nearly three-week arbitration hearing, Chris helped the construction manager obtain a Final Award of over $10 million on its affirmative claims. The Final Award overturned the Owner's improper default termination claim and dismissed the Owner's $120 million counterclaim in its entirety.

Recent Publications and Presentations (Previous Five Years)

  • Presenter: "Acceleration & Mitigation of Project Delays," WPL Publishing Co. Webinar, February 2023.
  • Co-Author: Chapter 9, Design-Build Contracting with the Federal Government, in Design Build, Public-Private Partnerships, and Collaboration Handbook (Wolters Kluwer) (3d ed. 2022).
  • Co-Author: Chapter 10, Design-Build Contracting with the Federal Government, in 2019 Construction Law Update (Wolters Kluwer) (2019).
  • Speaker: “Extension of Time (EOT) Claims – Separating Fairy Tales from Facts,” 2019 AAA Construction Conference, Miami, FL, April 2019
  • Speaker: “Are Scheduling and Delay Protocols Poseidon’s Trident or an Achilles Heel?” and “Dispute Resolution: A Global Perspective,” Eighth International Society of Construction Law Conference, Chicago, IL, September 2018
  • Speaker: “Laissez Les Bons Temps Rouler? – What You Need to Know About Contracting Outside of the United States,” American Bar Association Forum on Construction Law Annual Meeting, New Orleans, LA, April 2018.
  • Co-Editor: American Bar Association Forum on Construction Law Division 13 (Government Construction) newsletter, June 2016 – June 2018.
  • Speaker: “Managing Risk in a Complex Global Environment,” Global Construction Summit (presented by Engineering News-Record), New York, NY, October 2017.
  • Co-Author: Chapter 25, Federal Government Construction Contracts Outside the United States, in Forum on Construction Law, American Bar Association, Federal Government Construction Contracts (3d ed. 2017).
  • Co-Author: “Time Is on (Their) Side: The United Kingdom’s Society of Construction Law’s Delay and Disruption Protocol 2.0,” The Construction Lawyer, Volume 37, Number 4, Fall 2017.
  • Session Chair: “Time-Related Obligations in Key Jurisdictions: An Update,” International Bar Association Annual Conference, Washington, DC, September 2016.

Disclaimer
Varela, Lee, Metz & Guarino updates the content of this website on a periodic basis. Any content i) is for informational purposes only and does not constitute legal advice; and, ii) is not intended to create, and your receipt and/or use of such content does not create, a lawyer-client relationship. You should not rely on any such content without first consulting a licensed attorney familiar with your particular facts and legal issues.